Forty West Builders Home Forty West Builders Story Forty West Builders Building Process Forty West Builders Communities Forty West Builders Models And Plans Forty West Builders Gallery Forty West Builders Xpress Homes Contact Forty West Builders
 
At Forty West Builders, our primary goal is to make the process of building your new home not only enjoyable but also easy to understand. In this section, you will find a step by step guide to each step of the home selection and building process and approximately how long you can expect those steps to take. Please keep in mind that every project is unique and therefore the time estimate can vary based on the size of home as well as other factors.

We know that our ability to ensure a successful and stress-free homebuilding experience for our customers is directly related to the amount of customer referrals and repeat business we experience. That is the lifeblood of our business and we work tirelessly to earn it.

Use the links below to navigate through the different steps of our building process

Planning Stage
Site Work
Foundation
Framing
Mechanical
Drywall
Exterior Finishing
Trim and Flooring
Pre-Finish
Final Finish
Pre-Delivery Orientation
Delivery
Planning Stage
(30-45 Days)
Architectural planning, engineering, permitting, initial scheduling and customer color/finish selections.
Site Work
(3-5 days)
Lot staked, trees and brush removed, excavation, haul off of excess dirt, if necessary
Foundation
(14-17 days)
Footings poured, foundation walls poured, waterproofing of foundation, foundation backfilled, rough plumbing installed (below basement floor), basement floor and garage floors poured, sump pit installed.
Framing
14-21 Days
Rough framing of exterior shell, interior walls framed, exterior trim and windows installed, framing inspection completed and customer framing walk conducted to address electrical needs and desires.
Mechanical
14-20 Days
HVAC ductwork and vents constructed, rough plumbing and drain lines installed, rough electric wiring completed and audio/video/security pre-wire installation.
Drywall
10-17 Days
Insualtion installed in walls and vaults, drywall hung and finished, floors scraped and home cleaned out, walls and ceilings primed and inspected.
Exterior Finishing
10-17 Days
Siding, stone and brick preparation and install. Includes foam caulking and sealing exterior penetrations.
Trim and Flooring
10-14 Days
Trim constructed, hardwood floors laid, tile installed, paint interior and exterior, kitchen installed.
Pre-Finish
7-10 Days
Plumbing fixtures installed, electric finished and lighting fixtures hung, HVAC system completed, audio system completed, appliances installed, door and cabinet hardware installed.
Final Finish
4-7 Days
Final grading, landscaping and lawn installed. Carpeting completed, windows scraped and cleaned, entire home cleaned, paint touch-up.
Pre-Delivery Orientation
1-2 Days
On-site home orientation conducted with project superintendent. Customer questions addressed and preparations are made for final delivery.
Delivery
1 Day
Review and explanation of the Home Warranty, final completion of any outstanding paperwork and formal delivery of keys.
 
8311 Old Frederick Road
Ellicott City, MD 21043
PALMER RIDGE

$599,900
Go To Detail